Home/Track record/Flagship project

Flagship project · Melbourne's northern corridor, Victoria

A gigawatt AI campus designed around its power.

A single greenfield freehold beside a 500 kV transmission corridor, with a formal 1,000 MW connection response from the state's transmission planner already in hand. Built as repeatable 250 MW modules towards 1 GW of IT load, with gas firming and 500 MWh of battery storage fed from a new 500 kV terminal station — the power process was run first, so the campus can be.

1,000 MWMaximum demand assessed — connection feasible
4 × 250 MWRepeatable modules to 1 GW IT
500 MWhGrid-forming battery storage on site
36 monthsApplication to first energisation

CAMPUS FLY-THROUGH · MASTERPLAN VISUALISATION · INDICATIVE

Why this site

Australia has no shortage of planned data centres. It has a shortage of energisable land — and a gigawatt, transmission-assessed greenfield site in metropolitan Melbourne is close to unrepeatable.

Victorian pipeline9 GW+of planned data-centre capacity; only ~0.7 GW expected online by 2030
Connection queue5.4 GWlarge loads waiting nationally; Victoria ≈ 40 %
Data-centre demand4 → 12 TWhFY25 to FY30, growing ~25 % a year
Contingency limit600 MWevery larger load needs multiple connection points
  • 01 · 500 KV BACKBONEThe transmission line is 1 km away

    Loads above 500 MW are unlikely to be supported on 220 kV-only terminal stations; they need 500/220 kV transformation. Few metropolitan parcels sit beside a vacant 500 kV easement.

  • 02 · FIRST MOVEROne new terminal station per radius

    The transmission planner will not support over-concentration of shared terminal stations. The first proponent to lock a location becomes the hub others connect to.

  • 03 · FORMAL RESPONSERules-based, not a desktop enquiry

    Most pipeline sites hold nothing more than an informal enquiry. This one holds a formal Connection Enquiry Response under the National Electricity Rules, with quantified system-strength and fault-level figures.

  • 04 · SINGLE TITLEOne surveyed freehold lot, ~70 ha

    No amalgamation risk and only two registered easements. Feature and contour survey complete; planning pathway identified under the state's development facilitation programme.

  • 05 · GAS CONFIRMEDOn-site generation has a scoped pipeline

    The gas network has confirmed the volume needed for 300 MW of firming via a new pipeline — the generation layer is engineered, not a concept.

  • 06 · THE CORRIDORWhere the hyperscalers are already going

    Global cloud operators and Australia's largest data-centre developers are all committed to Melbourne's northern corridor. This site sits closer to the CBD than the corridor's largest announced parcel.

Three supply layers

Transmission, distribution and on-site generation back each other up.

If the transmission programme lags, the campus starts on interim distribution supply and on-site generation, then transfers load to the 500 kV connection as it energises. No single bet.

Primary · Transmission

New 500 kV shared terminal station

Cut-in to the adjacent 500 kV line, campus supplied at 220 kV. A contestable asset built by a nominated transmission service provider; indicative commissioning window 2029 under the planner's default programme.

Interim · Distribution

Staged distribution pathway

4 MVA accessible today from two substations already inside the boundary. The distributor has responded to a 1,000 MVA enquiry with a staged pathway — interim supply, sub-transmission development, dedicated terminal station — and offered to lead the feasibility study.

Contingent · On-site

Gas firming 3 × 100 MW + 500 MWh BESS

Gas volume confirmed achievable via a new 6–8 km pipeline. A grid-forming battery provides frequency response, black start and peak shaving — and is the natural remediation asset for the system-strength obligation.

Campus power architecture

500 kV in, 220 kV across the campus, 33 kV into each building.

Two independent 220 kV supplies to each of four buildings. Every 250 MW block has its own 220/33 kV substation; storage and generation sit on the same 220 kV campus bus.

Existing 500 kV transmission line · ~1 km from the boundary New 500 kV declared shared terminal station≤ 22 ha · breaker-and-a-half · 3–4 connection points 500 kV cables ≈ 1 km On-site 500/220 kV switchyardinside the title Gas firming3 × 100 MW BESS500 MWh grid-forming 220 kV campus bus — 8 feeders, 2 per building Building 1220/33 kV · 250 MW Building 2220/33 kV · 250 MW Building 3220/33 kV · 250 MW Building 4220/33 kV · 250 MW Distribution supply — 4 MVA today,interim 22 / 66 kV during construction Solar PVrooftop / batter Masterplan intent as put to the network operators. N-1 incoming feeders,four 250 MW data-hall blocks, 3 × 100 MW gas firming, 500 MWh BESS. Schematic.

500 kV terminal station

  • 500 kV, 220 kV and 66 kV switchyards
  • Provision for reactive compensation
  • Sized for the ultimate breaker-and-a-half arrangement including third-party bays

On-site 500/220 kV switchyard

  • Incoming feeders from the terminal station
  • 500/220 kV transformation
  • Eight outgoing 220 kV feeder circuits

Building substations 220/33 kV

  • Two independent 220 kV supplies per building
  • MV switchroom with 2-hour fire-rated panels
  • 33 kV distribution to data halls, gas plant and BESS

The authorities have answered

Every service confirmed feasible. The 1 GW grid response is in hand.

The technical and regulatory groundwork that usually takes a developer years is already done. What remains is execution — pre-application, planning lodgement, feasibility studies, construction approval and the terminal-station build.

ServicePositionOutcome
Grid · transmission1,000 MW Connection Enquiry lodged April 2026; formal response received June 2026 under NER clause 5.3.3. New 500 kV terminal station defined as the pathway; three arrangements assessed, all feasible; contingency limit and system-strength figures quantified.Feasible · formal response
Grid · distributionDistributor responded on interim supply for construction and commissioning and an initial portion of IT load; offered to lead the feasibility study.Staged pathway
GasNetwork confirms the volume required for 300 MW of firming is achievable via a new 6–8 km pipeline.Feasible · quantified
Water & fireHigh-water-user request; joint assessment with the metropolitan water authority under way; main extension and storage sized to achievable flow.Feasible · developer-funded extension
Sewer & stormwaterExtension routes identified; early engagement on discharge rates and detention.Feasible
CommunicationsAll major carriers have pit-and-pipe at the boundary; point-of-entry needs can be met.Feasible
Land & planningSingle freehold lot, surveyed. Planning pathway identified under the state's development facilitation programme — the same route the corridor's largest announced campus is using.Pathway identified

Australian benchmark

Against every campus under construction in Australia, this is first-tier scale — and the only grid-connected one with generation designed in.

  • This campus — masterplan
    1,000 MW
  • Largest off-grid project, NT
    1,000 MW
  • Largest under construction, Sydney
    400 MW
  • Largest in Melbourne, west
    354 MW
  • Melbourne west campus two
    300 MW
  • Melbourne west, second operator
    252 MW
  • Port Melbourne
    162 MW

Capacities as published by each operator (industry construction snapshots, 2026). Every listed grid-connected campus relies on diesel standby; this project designs gas firming and 500 MWh of BESS into the campus.

The 250 MW module

One module, repeatable four times within the 1 GW response.

Each module is a 250 MW data-hall block with its own 220/33 kV substation — sized to sit inside the 600 MW contingency limit and the planner's staged-load profile, so every repeat follows the same engineering, the same approvals and the same supply chain.

Module 1 · 250 MW

Months 0–36. New terminal station → 500/220 kV switchyard → BESS and Building 1 substation. Interim distribution supply and 3 × 100 MW gas firming during construction.

~17,870 GPUs · 17 CLUSTERS OF 128 NODES

Repeat 1 · 500 MW

After first energisation, inside the 600 MW contingency limit; terminal station at 220 kV to the campus, 2–3 connection points.

~35,700 GPUs CUMULATIVE

Repeat 2 · 750 MW

With the third connection point and the planner's staged-load profile; 500 kV line reinforcement scope.

~53,600 GPUs CUMULATIVE

Repeat 3 · 1 GW

With the regional terminal-station transformer upgrade (2031) and the ultimate breaker-and-a-half arrangement.

~71,500 GPUs CUMULATIVE

Ways to participate

Four structures that can be combined.

A · Energy partner

Behind-the-meter power JV

Co-own gas generation, BESS and on-site transformation; sell to the campus under a long-term PPA or tolling agreement. Infrastructure yield plus the right to tell the story as the energy-system owner.

B · Equipment + equity

Preferred supplier with a minority stake

Preferred supply of BESS, PCS, inverters and substation equipment, with minority equity in the project company. Export track record plus durable naming rights.

C · Devco equity

Development-stage investment

Enter before the planning application and participate through land, connection and approvals — capturing the step-up from "feasible" to "approved". Suits an investor building an Australian platform.

D · Showcase anchor

Technology demonstration and naming

A smaller commitment in exchange for energy-system naming, an on-site demonstration centre, joint announcements and industry-event priority. Suits brand and market-entry objectives.

Hard, quantified needs

System strength on 1,800 MVA, a 600 MW contingency, power-factor and reactive limits, interruptible-load duties — all written into the transmission response. Storage and power electronics are engineering requirements here, not a sustainability add-on.

OECD market, public rulebook

The planner's, market operator's and network's documents are public and verifiable — credibility that carries into Middle East and South-East Asian markets.

World's third-largest storage market

The national battery fleet passed 9 GW in mid-2026 with 33 GW of standalone storage in the connection queue, three-quarters of it grid-forming.

Important notice. This page is prepared from the project's Existing Infrastructure Review for preliminary information only. It is not an offer, investment advice or a commitment of any kind. The Connection Enquiry Response is a preliminary assessment under NER clause 5.3.3, not an agreement to augment the Declared Shared Network. Responses from network and utility operators are preliminary, indicative and non-binding and do not confirm availability of supply. All capacities, areas and timeframes are indicative and subject to change. Site identification, commercial terms, budgets and valuation are available under NDA only.

Power first. Then the campus.

Data room, technical workshop and participation structures for qualified energy, equipment and infrastructure partners.

Talk to the project team