Home/AIDC chain

The AIDC chain

Eight links from the transmission line to the token.

An AI data centre is a power project, a construction project, a hardware project and a software operation at the same time. QORINAI is organised around all eight links so that nothing falls between contracts.

500 kVconnection pathways we design for
2.5 MWtransportable module, redeployable
150 kWdirect-to-chip rack design point
< 1.10PUE tested on partner pod design

Link 01 · Land & power

The power process runs first.

State pipelines carry gigawatts of planned data-centre capacity; only a fraction will be energised this decade. The binding constraint is a formal, rules-based connection — so that is the first thing we secure.

Enquiry scale4 MVA → 1 GWfrom distribution feeders to a new terminal station
Supply layers3transmission · interim distribution · on-site generation
1.1

Site selection & due diligence

Freehold parcels beside EHV corridors, zoning and overlay review, easements, topography, water and sewer capacity, carrier pit-and-pipe. We screen for a site that can be energised, not just built on.

Planning pathwayEasement reviewWater & sewer
1.2

Connection enquiries & studies

Transmission connection enquiries under the National Electricity Rules, distribution enquiries with the local network, connection-option assessment (new terminal station cut-in vs 220 kV extensions), contingency limits, fault-level ratings, power-factor and reactive requirements, system-strength charges versus remediation schemes.

NER 5.3.3 enquiries500 / 220 kV optionsSystem strengthPSS/E · PSCAD
1.3

Energy architecture

Three supply layers that back each other up: the transmission connection as the end state, an interim distribution pathway to start construction and early IT load, and on-site gas firming with battery storage so the campus can ramp on schedule. Behind-the-meter power stations and take-or-pay PPAs where the site allows.

Gas firmingGrid-forming BESSBehind-the-meter PPAInterruptible load
1.4

Staged energisation plan

Loads above the credible-contingency limit must be split across multiple connection points and ramped on an agreed profile. We plan the campus in power blocks so the first block is live while later blocks are still in application.

≥ 3 connection points for 1 GWRamped load profile

Link 02 · Design

Halls designed for the rack you'll deploy next.

Tier III+ concurrently-maintainable MEP with three cooling tiers in every campus, so storage, networking and GPU racks each get the right plant — and no hall is rebuilt when the next accelerator lands.

Tier A · Air≤ 30kW / rack

Air-cooled hall

Hot-aisle containment for storage, networking, PCIe GPU and CPU nodes.

Tier B · RDHx30–80kW / rack

Rear-door heat exchange

Liquid-assisted air cooling for HGX B200 / B300 air-cooled nodes without changing the server.

Tier C · DLC80–150kW / rack

Direct-to-chip liquid

CDU per row, secondary loop manifolds, 415 V busway. Built for GB300 NVL72 and beyond.

Design basisTier III+ concurrently maintainable · 99.99 % availability design target · phased 10–50 MW power blocks
ReticulationCampus supplied at 220 kV · on-site 500/220 kV switchyard where required · 220/33 kV building substations · two independent supplies to every hall · 33 kV to data halls, gas plant and BESS
PowerDual A+B feeds to every rack · 2N UPS · N+1 generation with 48 h fuel · 415 V 3-phase busway · reactive compensation / STATCOM-class control
CoolingN+1 CDUs per row · warm-water DLC (30–40 °C supply) · rear-door heat exchangers · free-cooling chillers · design PUE ≤ 1.2, partner pod design tested below 1.10
NetworkCarrier-neutral meet-me room · 40 Gbps+ cross-connects · dark fibre to metro exchanges · diverse duct routes
Security24×7 manned · biometric and mantrap access · facial recognition and thermal imaging · CCTV retention · ISO 27001-aligned operations
Fire & safetyVESDA very-early smoke detection · clean-agent gas suppression in data halls · leak detection on every liquid loop · 2-hour fire-rated MV switchrooms

Link 03 · Build

Modular blocks, owner-managed delivery.

Two delivery lessons from our partners' projects shape every QORINAI build: transportable modules get a site energised in months, and direct management of specialist subcontractors removes the master-EPC margin and keeps the liquid-cooling know-how in house.

Transportable 2.5 MW modules

Factory-built modular data centres — each a self-contained 2.5 MW unit with its own distribution, cooling and security envelope. Eight modules deliver 20 MW; each can be dismantled, refurbished or redeployed. Designed for Australian climate conditions and regional sites.

SIGNED → FIRST POWER IN DAYS

Modular launch on existing supply

Where a site has distribution capacity today, a 2.5–3 MW modular launch goes live on a 14-month application-to-completion programme while the transmission connection is in process — early revenue on behind-the-meter power.

14-MONTH PROGRAMME

Campus power blocks

Large campuses are built as repeatable 10–50 MW blocks, each with its own substation capacity, cooling plant and data hall, so capital is committed in phases and tenants are live while later blocks are in the ground.

10–50 MW BLOCKS
Conventional

Master EPC

  • 10–20 % EPC margin on every trade
  • Interface costs between owner, EPC and subcontractors
  • Slow change response — liquid-cooling iterations wait for variations
  • Technical know-how stays with the EPC
QORINAI model

Owner-managed subcontracting

  • Electrical, mechanical / liquid cooling, cabling and compliance trades engaged directly
  • No master-EPC margin or interface cost
  • Design changes resolved on site, same week
  • Know-how accumulates in our runbooks and product designs
  • Proven subcontractor bench re-used on the next cluster

Link 04 · Hardware

Open-OEM systems, Australian stock.

Through our strategic shareholder Hyperscalers we specify, configure and warrant NVIDIA and AMD platforms locally — no grey imports, no offshore RMA queues.

HGX B300 serverMI325X server400G switchJBOD
  • NVIDIA HGX B300 and B200 8-GPU nodes on Intel Xeon 6 / AMD EPYC 9005
  • NVIDIA GB300 NVL72 rack-scale systems, liquid-cooled
  • AMD Instinct MI325X 8-GPU, NVIDIA GH200 Grace Hopper MGX
  • H200 NVL and RTX PRO 6000 Blackwell PCIe servers for inference and rendering
  • Quantum InfiniBand XDR and Spectrum-X 800G Ethernet fabrics, BlueField-3 DPUs
  • ONIE / Cumulus bare-metal switches 1G–400G, OCP open-rack systems
  • NVMe all-flash and 4U JBOD storage, parallel file systems
  • Lab-as-a-Service: test-drive the configuration before you buy

Link 05 · Deploy

Handed over benchmarked, not boxed.

A cluster is not delivered when the pallets arrive. It is delivered when every node has passed thermal soak, every NVLink and fabric link is clean, and the all-reduce numbers match the datasheet.

5.1

Rack & power

Rack elevations, busway tap-offs, A+B PDU balancing, liquid manifold and quick-disconnect fit-out for DLC nodes.

5.2

Fabric build

Rail-optimised InfiniBand XDR or 800G RoCEv2 Ethernet, 1:1 non-blocking, dual-routed inter-hall links, separate north-south and management networks.

Rail-optimised1:1 non-blockingDual-routed
5.3

Burn-in & validation

Firmware baseline, DCGM diagnostics, NCCL all-reduce, HPL / HPL-MxP, thermal soak under sustained load, link-error audit. Results documented per node.

NCCLHPLDCGMThermal soak
5.4

Platform handover

Scheduler (Slurm or Kubernetes), storage mounts, tenant isolation, monitoring and runbooks in place on day one — for our operations team or yours.

Link 06 · Operate

GPUs are only an asset when they are busy.

A B300 node that sits idle, throttles on a warm coolant loop or waits three weeks for an RMA is a depreciating liability. We run GPU fleets the way a utility runs a grid: measured continuously, maintained before failure, reported monthly to the owner.

Node availability99.9 %monthly SLA
P1 response< 15 minon-site engineer
General SLA< 4 hsmart hands

What we measure on every GPU

  • SM occupancy and tensor-core utilisation
  • HBM temperature, ECC and row-remap counts
  • NVLink / NVSwitch link errors and retrains
  • Xid faults and driver resets
  • Power draw per GPU, tray and rack
  • Coolant supply temperature and ΔT per CDU
  • Fabric health — link flaps and congestion
  • Job throughput and queue depth

Fleet management services

  • 24×7 NOC with DCGM-based monitoring and alerting
  • Firmware, driver and CUDA lifecycle management
  • Vendor RMA management with hot spares on site
  • Scheduler operations — Slurm, Kubernetes
  • Utilisation and health reporting for asset owners and lenders
  • Secure tenant offboarding, data wiped in Australia

Link 07 · Host

Colocation and capacity hosting at GPU density.

Quarter rack to private suite, 30–150 kW per rack, dual A+B feeds, carrier-neutral cross-connects and Australian engineers on site around the clock.

Footprints

Quarter rack · half rack · full rack · multiple racks · private cages and suites.

Power & cooling

Dual-feed standard, up to 150 kW per rack on DLC halls; redundant cooling plant.

Connectivity

40 Gbps+ cross-connects, dark fibre, IP transit, access to major Australian and international carriers.

Smart hands

< 15 min P1, < 4 h general — installs, cabling, power cycling, diagnostics by Australian engineers.

Link 08 · Compute

Sovereign AI and cloud on the infrastructure we build.

The end of the chain is compute a customer can rent by the GPU-hour, the node or the month — hosted in Australia, billed in AUD, with no prompt caching and no training on your data.

Sovereign AI

  • GPU-as-a-Service — reserved pools, AUD billing
  • GPU & CPU clusters for training
  • GPU compute from a single GPU to full nodes
  • 100+ frontier and open-weight models

Sovereign cloud

  • Virtual machines — sub-60-second provisioning
  • Private cloud — dedicated OpenStack tenancy
  • Block storage, S3-compatible object storage
  • Disaster recovery & immutable backup

HPC & rendering

  • Compute that doesn't queue
  • Burst VFX rendering for studios
  • Bare metal dedicated — no hypervisor
  • Low-egress, predictable AUD pricing

Start at whichever link you're on.

Land without power, power without a hall, a hall without GPUs, or GPUs without an operator — we pick up the chain from there.

Talk to engineering